Federal government ducks Lower Thames Crossing choice

CGI of the northbound website of the proposed Lower Thame Crossing

It is now clear that when Keir Starmer in opposition stated “we select the home builders, not the blockers” he was talking just about house-building. Significant shovel-ready facilities jobs prepared to increase the economy are either being ditched or kept in the beginning gates.

Starmer’s Labour Party was voted into power on 4th July this year and before completion of the month the ₤ 2.5 bn A303 Stonehenge tunnel and the ₤ 350 A27 Arundel bypass had actually been ditched.

Now we have verification that the federal government is unsteady on the greatest roadway structure task in the program, the ₤ 9bn Lower Thames Crossing plan.

The choice on the application by National Highways under the Planning Act 2008 for the A122 Lower Thames Crossing advancement permission order was due on Friday 4th October. On Monday 7th October transportation secretary Louise Haigh validated press reports that she was not yet all set to phone on the questionable task.

She has actually extended her due date for deciding to 23rd May 2025.

The previous federal government had actually currently extended the due date for a choice by 3 months as soon as, to press it back to after the basic election.

Now Haigh states she is parking it up until next May due to the fact that she desires more time to choose.

In a composed declaration, Haigh stated: “Under area 107( 1) of the Planning Act 2008, a choice on an application need to be made within 3 months of invoice of the taking a look at authority’s report, unless the power, under area 107( 3 ), is worked out to extend the due date, and a composed ministerial declaration is made to Parliament revealing the brand-new due date.

“The analyzing authority’s report on the Lower Thames Crossing advancement authorization order was gotten on 20th March 2024. The existing due date for a choice is 4th October 2024, having actually been extended from 20th June 2024 by method of a composed ministerial declaration, dated 24th May 2024.

“The due date for the choice is to be additional encompassed 23rd May 2025 in order to enable more time for the application to be thought about even more, consisting of any choices made as part of the costs evaluation.

“The choice to set a brand-new due date lacks bias to the choice on whether to approve the application advancement approval.”

The Lower Thames Crossing has actually remained in the works for 35 years, because Margaret Thatcher’s transportation secretary Paul Channon’s Roadways for Prosperity white paper in 1989.

The job as presently prepared includes the building and construction of a twin bored tunnel under the River Thames to the east of Tilbury and Gravesend, plus 14.3 miles of brand-new roadways to connect it to the M25 and A13 (to the north of the river) and the M2/A2 (to the south). At a length of 4.3 km it would be the longest UK roadway tunnel and with a size of more than 16 metres,

» …